Park, building and road projects -21-22

Council completes a wide range of construction projects each year to deliver new and improved services to the community and maintain and renew infrastructure assets. The table below provides project details. 

In 2021-2022 Council plans to deliver $45.3 million in works. As at 31 May 2022, $29.3 million has been spent. 

You can also link to the monthly finance report for the 2021-2022 financial year here:

Monthly finance report

Council is committed to delivering effective, efficient services that meet the expectations and needs of the community. As part of that commitment, Council is providing information on the capital works program to ensure open and transparent communication with the community.

2021-2022 project information (parks, buildings and roads)

Progress legend

On track – On track
Behind schedule – Behind schedule
On hold – On hold
Rescheduled – Rescheduled
Completed – Completed

Monthly financial report legend

Month – Financial status for the 2021-2022 financial year is reported to the end of month indicated
Works or engagement notification only – Works or engagement notification only; refer to the relevant program page line for financial information
Black square – Greenway budget for 2021-2022 financial year is $3.3  million. As at 31 May 2022, $2.6 million has been spent. 
Black triangle – Urban Amenity Improvement Program budget for 2021-2022 financial year is $9.1 million. As at 31 May 2022, $7.4 million has been spent.

Suburb Location Type of work Anticipated completion Status Progress Budgeted 2021-2022 ($,000) Full Year Spent 2021-2022 ($,000) May-22 Further information
Multiple suburbs Carpark Carpark Renewal Jun 2022 Completed Completed 210
137 Car Parks Renewal Program
Multiple suburbs Footpaths Footpath Renewal and Upgrade Jun 2022 Works in progress On track 3,371 1,009 Footpath Renewal & Upgrade Program
Multiple suburbs Playgrounds Playgrounds renewal and upgrade Jun 2023 Works in progress On track 320 305 Playground program
Multiple Suburbs Park Footpath Park Footpath Renewal Jun 2022 Near Completion Rescheduled 673 314 Park Footpath programs
Multiple Suburbs Regional and local roads Road renewal Jun 2022 Works in progress On track 6,525
4,735
Regional and Local Roads Program
Multiple suburbs Council childcare centres and other buildings Solar power and LED lighting upgrades Jun 2023   Works commencing On track   200 116  Solar and energy efficiency programs
Multiple Suburbs Stormwater Stormwater Renewal and Upgrade   Jun 2022 Works in progress  On track   2,168 1,289 Stormwater programs
Multiple Suburbs Traffic Facilities Traffic and Pedestrian infrastructure Jun 2022 Works in progress On track      Traffic Facilities programs
Annandale Booth Street Bridge widening Jun 2022 Works in progress Behind schedule 1,090
1,060 Booth Street Bridges
Annandale
Cahill Street Playground

New open space

playground upgrades

Dec 2022 Design On track 50 66 New public spaces projects
Annandale

Johnstons Creek -

Booth Street

Wigram Road

PRUAIP-New cycleway,

Badu Park

Jul 2022 Works in progress Behind schedule Black triangle
Black triangle

PRUAIP Johnstons Crks

Ashfield Ashfield Aquatic Centre 

Shade

car park

improvements

Oct 2022 Works in progress On track 398
187

Ashfield Aquatic Centre project page - Completed

Ashfield Aquatic Centre Phase 2 

Ashfield Hammond Park

Installation 

Fencing

Mar 2022 Work Commencing On track Works or engagement notification only Works or engagement notification only Hammond Pk notification (PDF 593.4KB)
Ashfield
Lewis Herman Reserve

New park facilities

investigation of off-leash area

Dec 2022
Procurement
On track
Works or engagement notification only Works or engagement notification only New public spaces projectss
Ashfield Yeo Park Park Masterplan Upgrades Jun 2023 Planning On track 43
15
Yeo Park projects
Balmain Balmain Plaza New plaza Jul 2021 Completed Completed 15
6
Telstra site public spaces
Balmain Balmain Town Hall

Ground floor  -

library upgrade,

building renewal works

planning.

June 2024 Procurement & Engagement On track -
-
Balmain Town Hall upgrade
Balmain

Dawn Fraser Baths 

Elkington Park 

Access improvements

Northern pavilion

refurbishment

Dec 2023
Design On track
179
544 Dawn Fraser Baths projects
Balmain Gladstone Park

Upgrade of junior

teenager play spaces

Feb 2022 Completed Completed Works or engagement notification only Works or engagement notification only Playground programs
Balmain Gladstone Park New Public Toilets  Jul 2023  Consultation On track  15 -

Gladstone Pk Amenities projects

Balmain Paringa Reserve

Demolition of former

Pelegrinis Restaurant

construction of new kiosk

& public toilet.

Jun 2023 Design On track 44
20 Elliot Street Kiosk
Balmain East

Darling Street

Main street upgrade Sep 2021 Completed

Completed

300 294

Balmain East Town Centre projects

Birchgrove Birchgrove Park

Sports field

fencing renewal

Jun 2022 Works in Progress

Behind schedule

316
263

 Birchgrove Park projects


Works Notification (PDF 459.7KB)

Birchgrove Birchgrove Park Stormwater Drainage works Apr 2022 Completed Completed Works or engagement notification only Works or engagement notification only  Stormwater programs
Camperdown Pyrmont Bridge Road

PRUAIP-New cycleway

Parramatta Rd to Mallet St

Dec 2023 Concept Design On hold Black triangle
Black triangle
Camperdown Cycle Way
Dulwich Hill

Dulwich Hill Station Precinct

Wardell Rd 

Dudley St

Ewart St.

Improvement to cycleway

various traffic management

public domain

Nov 2022 Works in Progress On track 450
314 Dulwich Hill Station Precinct 
Dulwich Hill
Hoskins Park

Park Upgrade

Dec  2023
Planning
On track 20
8 Hoskins Park
Dulwich Hill Johnson Park Park Masterplan upgrades Jun 2023 Procurement On track  -
4 Johnson Park Upgrade
Dulwich Hill

Deborah Little

Early Learning

Centre

Childcare centres

renewal and upgrade

Jun 2022 Planning On track Works or engagement notification only Works or engagement notification only Children's Services Work Program projects
Dulwich Hill

GreenWay

between Waratah Mills /

Dulwich Hill

High Voltage Electrical Feeder relocation Sep 2022 Works in progress On hold Black square
Black square

GreenWay website
GreenWay Your Say Inner West

Dulwich Hill GreenWay Local streets Traffic and streetscape improvements Jan 2022 Completed Completed Black square
Black square
GreenWay website
GreenWay Your Say Inner West
Dulwich Hill, Lewisham, Summer Hill, Leichhardt

GreenWay In-corridor works

between Taverners Hill /

Dulwich Hill

Path, lighting,

landscape and art works

Apr 2025 Procurement Behind schedule Black square
Black square
GreenWay website
GreenWay Your Say Inner West
Haberfield Algie Park Playground upgrade Mar 2022 Completed Completed 80
78 Playgrounds renewal and upgrade projects
Haberfield, Lilyfield

GreenWay and

Bay Run path

Bay Run path and lighting upgrade Jan 2023 Works in progress On track Black square
Black square
GreenWay website 
Greenway Your Say Inner West
Leichhardt

Balmain Road
Catherine Street
Crystal Street
Norton Street

Completed

Renwick Street
Rofe Street

PRUAIP - North South Streets,

Various Upgrades of Streets off Parramatta Road

Sep 2022

Works in Progress

* Ausgrid Outage on Catherine Street has been delayed

On track Black triangle
Black triangle
PRUAIP North South Streets
Leichhardt Dot Lane

PRUAIP-Cycleway

various upgrades off Parramatta Rd

Jul 2022 Works in progress On track Black square
Black square
PRUAIP - Dot Lane Cycleway
Leichhardt Parramatta Road Various upgrades Jun 2024 Works in progress On track Black square
Black square
Parramatta Road Urban Renewal webpage
Leichhardt

Leichhardt Park

Aquatic (LPAC)

Mary Street 

Aquatic centre upgrade Dec 2023 Planning

On track

100
33 Leichhardt Park Aquatic project
Leichhardt

Leichhardt Park

Children's Centre

Shade Sail upgrade

Jul 2022 Procurement On track Works or engagement notification only Works or engagement notification only Children's Services Work Program project
Leichhardt Leichhardt Town Hall

External lighting.

Kitchen and acoustic panel renewals

Dec 2022 Design On track 16 12 Leichhardt Town Hall project
Leichhardt Leichhardt Oval No. 1 Male and female amenities upgrades Jun 2023 Design On track 20
7
Leichhardt Oval project
Leichhardt Pioneers Memorial Park Playground upgrade Feb 2022 Completed Completed
Works or engagement notification only Works or engagement notification only

Playground program page

Works Notification (PDF 1.4MB)

Leichhardt Pioneer Memorial Park New Public Toilets Sep 2022 Procurement  On track 100 104  Pioneer Park New Public Toilets
Lewisham to Newtown Longport Street to Petersham Station Cycleway construction Jun 2022 Completed Completed Works or engagement notification only Works or engagement notification only Lewisham to Newtown cycle link
Lilyfield Lilyfield Road Construction of cycleway 2023 Design On hold Works or engagement notification only Works or engagement notification only Route D3 Iron Cove to Anzac Bridge
Lilyfield Lilyfield Skate Plaza Skate facility with weather shelters and lighting Dec 2022 Design On track   30 70 Lilyfield Skate Plaza 
Lilyfield, Rozelle
The Bay Run
Lighting upgrade through Leichhardt Park and King George Park Jun 2022
Procurement
On track
-
31 New public spaces projects
 Marrickville Addison Road Bioretention Pond  Oct 2022  Works Commencing  On track

 Addison Rd CC Bioretention project

Works notification (PDF 826.8KB)

Marrickville Alex Trevallion Plaza Plaza upgrade Sep 2021 Completed Completed 800 788
Alex Trevallion Plaza project
Marrickville

Annette Kellerman

Aquatic Centre

Aquatic Centre Upgrade Oct 2022 Planning On track 20 6 Annette Kellerman Aquatic Centre Project
Marrickville

Marrickville Road East -

Meeks Road to

Sydenham Station

Cycleway and Streetscape Improvements Jun 2023 Design On track 20
12
Marrickville Road East Your Say Inner West
Marrickville

Livingstone Road

Fraser St to Randall St

Cycleway construction Jun 2022 Works in progress On track 1,900 843

Livingstone Road Cycle Path project

Works notification (PDF 229.2KB)

Marrickville Dibble Avenue Waterhole Waterhole stabilisation Oct 2021 Completed Completed
Works or engagement notification only Works or engagement notification only Dibble Avenue project
Marrickville

Globe Wilkins

Preschool

Design and Construction Jul 2022 Completed Completed Works or engagement notification only Works or engagement notification only Children's Services Work Program project
Marrickville

HJ Mahoney

Memorial Reserve

Amenities upgrade Dec 2022 Design On track 62 20 HJ Mahoney Reserve project                                                           .
Marrickville Henson Park Sports field upgrade Dec 2021 Completed * Completed 195 68

Henson Park project

* except for Sand Slit drains

Marrickville Herb Greedy Hall
Facility refurbishment Jun 2022 Design On track 25
8 Herb Greedy Hall Upgrade project
Marrickville Mackey Park Park Masterplan Upgrades Feb 2023 Planning On track - -
Mackey Park Upgrade project
Marrickville

Marrickville Town Hall

St Peters Town Hall

External renewal works 2021-2022.
Apr 2023 Procurement On track 215 2 Marrickville & St Peters Town Hall project
Marrickville Warren Road

Carrington Road to Illawarra Road,

one-way westbound traffic.

Apr 2022 Completed Completed 195 101

Warren Road project

Works notification   (PDF 222KB)

Newtown Newtown Town Hall

Town Hall compliance and upgrade works

in coordination with proposed Pride Centre

Mar 2023 Planning On track 168
4 Newtown Town Hall and Tom Foster Community Centre project
Newtown

Camperdown

Memorial Rest Park

New public toilet Oct 2022 Construction On track 500
82 Camperdown Memorial Rest Park new facilities 
Petersham

KU Petersham

Preschool

Structural rectification

building condition works

Jun 2023 Planning On track Works or engagement notification only Works or engagement notification only Children's Services Work Program project
Petersham Petersham Street

PRUAIP-Road closure

construction of Pocket Park

Aug 2022 Works in Progress On track Black triangle
Black triangle
PRUAIP - Petersham Street Plaza project


Petersham Petersham Town Hall

Masterplan upgrade

 compliance works

Jun 2023 Planning On track 15
4 Petersham Town Hall project
Petersham

Parramatta Road- Marrickville Park

via West Street

Cycleway construction Jun 2022 Design On track -
-
Regional bike route 2 Your Say Inner West
Rozelle Easton Park Sports field Upgrade Jun 2023 Procurement On track 20 2 Easton Park Upgrade project page
Rozelle King George Park Sports field upgrade Jun 2023 Procurement On track 50 26 King George Park Upgrade project
Rozelle

King George Park

Constellation Playground

Playground Upgrade Jun 2023 Planning On track Works or engagement notification only Works or engagement notification only Playground program page
Rozelle

Wulumaty Close,

Elliot Park

Park lighting renewal and upgrade Aug 2022 Works commencing On track 50
23
Elliot Park Lighting Upgrade project
St Peters Canal Rd/Princess Hwy/Mary St Cycleway construction Aug 2022 Design On track

WCX M5 - Canal Rd/Princes Hwy/Mary St Cycleway project
St Peters

Tom Foster

Community Centre

Community Centre renewal

upgrade for Newtown Neighbourhood Centre

Oct 2022 Procurement On track 400
87 Newtown Town Hall and Tom Foster Community Centre project
Summer Hill Darrell Jackson Gardens Park playground upgrade Nov 2022 Procurement On track Works or engagement notification only Works or engagement notification only Darrel Jackson Gardens Upgrade
Summer Hill

Summer Hill

Reuse Centre

New reuse &

recycling hub

Dec 2022 Construction On track -
163
Summer Hill Reuse Centre project
 St Peters Bedwin Bridge Cycle way Cycleway construction Dec 2022  Works in Progress On track  814 381 Bedwin Rd Cycleway project
Sydenham Sydenham Station Cycleway construction Aug 2022 Design On track

Sydenham Station Cycleway project
Tempe Tempe Reserve

Pedestrian lighting

renewal  & upgrade

Dec 2022 Procurement On track 50
39 Tempe Reserve  lighting project
Tempe Tempe Reserve

Synthetic &

natural turf

sports field

upgrade

Apr 2022 Completed Completed 2,950
2,725 Tempe Reserve sports field upgrade project
Tempe

Robyn Webster Building

Tempe Reserve

Refurbishment of  indoor sporting facility Jun 2023 Design On track 100
30 Robyn Webster Building project
Tempe Unwins Bridge Road Signalised Crossing Dec 2022  Works in Progress On track  Unwins Bridge Road Crossing Project

Rate this page

  • Rate as The content was useful63.64% The content was useful votes
  • Rate as The content was not useful36.36% The content was not useful votes

Thanks for your feedback. We will use this data to improve the content of this page.

Page last updated: 26 Apr 2023