2023-24 park, building and road projects

Council completes a wide range of construction projects each year to deliver new and improved services to the community and maintain and renew infrastructure assets. The table below provides project details.

In 2023-24 Council plans to deliver $111.2 million in works. As at 31 August 2023, $22.7 million has been spent.

Council is committed to delivering effective, efficient services that meet the expectations and needs of the community. As part of that commitment, Council is providing information on the capital works program to ensure open and transparent communication with the community.

2023-2024 project information (parks, buildings and roads)

Progress legend

On track – On track
Behind schedule – Behind schedule
On hold – On hold
Rescheduled – Rescheduled
Completed – Completed

Works or engagement notification only – Works or engagement notification only; refer to the relevant program page line for financial information

Black square – Part of the GreenWay project.

Black triangle - Part of the Urban Amenity Improvement Program.

Suburb Location Program Anticipated completion Status Progress  Budgeted 2023/24 ($,000) Full Year Spent 2023/24 ($,000) Jul-23  Spent 2023/24 ( $,000) Aug-23 Further information
Multiple suburbs Playgrounds Playgrounds renewal and upgrade Jun 2024 Works in progress On track  3,109  5  13 Playground Program
Multiple suburbs  Multiple Locations Pedestrian safety improvements Jun 2026 Works in progress On track  2,000  7 69 Pedestrian Access and Mobility Plan (PAMP) Program
Multiple suburbs

 Lewis Herman Reserve

Cahill Street Playground

Bay Run Lighting

 Public Spaces Project  Aug 2023 Works in progress On track  - (40)  5 New Public Spaces Project
Annandale Annandale Town Hall and Community Centre Refurbishment Jun 2025 Planning On track   670 -  -  Annandale Town Hall and Community Centre
Annandale Collins Street Footpath Renewal Sep 2023 Commencing On track  Works or engagement notification only  Works or engagement notification only  Works or engagement notification only Notification Letter  (PDF 248KB)
Balmain Balmain Town Hall

Ground floor  - library upgrade and building renewal works

Jun 2024 Design On track  1,370  - 26 Balmain Town Hall upgrade project
 Balmain Clayton Street Footpath Renewal Sep 2023 Works in progress
On track  Works or engagement notification only  Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 240.6KB)
Balmain

Dawn Fraser Baths - Elkington Park

Access improvements -Northern pavilion refurbishment

Oct 2024
Planning On track
 2,000 -  - Dawn Fraser Baths project
 Balmain Darling Street and Elliott Street Main Street Improvement Works  Sep 2023 Consultation On track  Works or engagement notification only Works or engagement notification only   Works or engagement notification only

Consultation Letter (PDF 289.9KB)

Consultation Plan (PDF 1.2MB)

 Balmain Elliott Street Intersection upgrade Oct 2023 Commencing On track   - - -

Notification Letter (PDF 151.1KB)

Notification Plan (PDF 509.9KB)

Balmain Gladstone Park New Public Toilets  Jun 2024 Planning On track   70 -  -

Gladstone Pk Amenities project

Balmain Paringa Reserve

Demolition of former Pelegrinis Restaurant. Construction of new kiosk and public toilet

Oct 2023 Construction On track  840  -  111 Elliot Street Kiosk project
Birchgrove Birchgrove Park

Sport field fencing

-
Completed Completed  -  10  1

 Birchgrove Park project 

 Birchgrove Birchgrove Park Amenities Upgrade and renewal   Jun 2026  Planning On track   120  -  - Birchgrove Park Amenities project
Camperdown Pyrmont Bridge Road

PRUAIP-New cycleway

Parramatta Rd to Mallet St

Aug 2025 Concept Design On hold  Black triangle Black triangle  Black triangle  Camperdown Cycle Way project
Dulwich Hill

Dulwich Hill Station Precinct

Wardell Road

Dudley Street

Ewart Street

Improvement to cycleway

Various traffic management

Public domain

Jul 2025 Works in Progress Behind schedule 1,000  9  145 Dulwich Hill Station Precinct  project
Dulwich Hill Hoskins Park

Park Upgrade

TBC

Procurement

and Design

On track  560 -  - Hoskins Park project
Dulwich Hill Johnson Park Park Masterplan upgrades Nov 2024 Design On track   Black square   Black square   Black square  Johnson Park Upgrade project
Dulwich Hill, Lewisham, Summer Hill, Leichhardt

GreenWay
In-corridor works between Taverners Hill and Dulwich Hill

Path, lighting, landscape and art works

Apr 2025 Procurement Behind schedule  Black square   Black square   Black square  GreenWay website
GreenWay Your Say Inner West
 Haberfield Dudley Street (1-3) Stormwater Drainage Improvements  Oct 2023 Consultation On track  - - -

Consultation Letter (PDF 199.6KB)

Consultation Plan (PDF 333.9KB)

 Haberfield Dudley Street (50-52) Stormwater Drainage Improvements  Oct 2023 Consultation On track - - -

Consultation Letter (PDF 197.8KB)

Consultation Plan (PDF 288.2KB)

 Leichhardt Flood Street Footpath Renewal Aug 2023 Completed Completed  Works or engagement notification only Works or engagement notification only  Works or engagement notification only   Notification Letter (PDF 254.9KB)
Leichhardt Hill Street Footpath Renewal Aug 2023 Completed  Completed  Works or engagement notification only Works or engagement notification only  Works or engagement notification only  Notification Letter (PDF 248.2KB)
 Leichhardt John Street Footpath Renewal Aug 2023 Completed Completed Works or engagement notification only  Works or engagement notification only  Works or engagement notification only   Notification Letter (PDF 240.5KB)
Leichhardt Parramatta Road Various upgrades Jun 2024 Works in progress On track  Works or engagement notification only  Works or engagement notification only Works or engagement notification only  Parramatta Road Urban Renewal
Leichhardt

Leichhardt Park Aquatic (LPAC)

Mary Street

Aquatic centre upgrade Jan 2024 Planning  3,695  1 8 Leichhardt Park Aquatic project
Leichhardt Pioneer Memorial Park New Public Toilets Dec 2023 Construction  On track  900  - - Pioneer Park New Public Toilets  
Lilyfield Lilyfield Road Construction of cycleway Mar 2025 Design Rescheduled 398   3 3 Route D3 Iron Cove to Anzac Bridge
Lilyfield O'Neill Street  Stormwater Drainage Upgrade Feb 2024 Commencing On track  800  - -

Notification Letter (PDF 1.4MB)

Notification Plan (PDF 1.2MB)

Lilyfield, Rozelle
The Bay Run
Lighting upgrade through Leichhardt Park and King George Park Aug 2023 Works in progress
On track
 Black square Black square  Black square  New public spaces projects
Marrickville

Annette Kellerman

Aquatic Centre

Aquatic Centre Upgrade  Jul 2024 Planning On track  3,950 -  12 Annette Kellerman Aquatics Project
 Marrickville Carrington Road Pedestrian Safety Aug 2023 Design On track Works or engagement notification only   Works or engagement notification only Works or engagement notification only 

Consultation (PDF 220.3KB)

Consultation Plan (PDF 732.3KB)

Marrickville Chalder Street Footpath Renewal Sep 2023 Works in progress On track  Works or engagement notification only  Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 247.5KB)
Marrickville

HJ Mahoney

Memorial Reserve

Sporting Ground and Amenities Upgrade Feb 2024 Procurement On track  3,310  -  14 HJ Mahoney Memorial Reserve Sporting Ground and Amenities Upgrade
Marrickville Mackey Park Park Masterplan Upgrades Jan 2024 Design On track  400 -  - Mackey Park Upgrade
Marrickville

Marrickville Town Hall

St Peters Town Hall

Town Hall Upgrades Aug 2023 Works in Progress On track  200 -  - Marrickville/ St Peters Town Hall External Upgrade
 Marrickville Petersham Road Stormwater Drainage Upgrade Nov 2023 Commencing On track - - Notification Letter (PDF 229.3KB)
Newtown Chelmsford Street Footpath Renewal  Sep 2023 Works in progress On track Works or engagement notification only  Works or engagement notification only  Works or engagement notification only  Notification Letter (PDF 240.9KB)
Newtown Commodore Street Footpath Renewal Sep 2023 Works commencing On track  Works or engagement notification only Works or engagement notification only  Works or engagement notification only  Notification Letter (PDF 240.8KB)
 Newtown Darley Street Footpath Renewal  Oct 2023 Works commencing On track Works or engagement notification only   Works or engagement notification only Works or engagement notification only   Notification Letter (PDF 248.4KB)
 Newtown Ferndale Street Footpath Renewal Sep 2023 Works in progress On track Works or engagement notification only  Works or engagement notification only  Works or engagement notification only  Notification Letter (PDF 240.5KB)
Newtown Holt Street Footpath Renewal Sep 2023 Commencing On track  Works or engagement notification only Works or engagement notification only  Works or engagement notification only   Notification Letter (PDF 240KB)
 Newtown  Laura Street Pedestrian Crossing  Sep 2023 Consultation  On track - -

Consultation Letter (PDF 216.2KB)

Consultation Plan (PDF 778.1KB)

Newtown

Newtown Town Hall

 

Town Hall compliance and upgrade works in coordination with proposed Pride Centre

Jul 2024 Procurement On track  3,220  3 7 Newtown Town Hall Pride Centre Refurbishment
Newtown Oxford Street Footpath Renewal Sep 2023 Commencing On track  Works or engagement notification only Works or engagement notification only  Works or engagement notification only  Notification Letter (PDF 240.1KB)
 Newtown Rawson Street Footpath Renewal Sep 2023 Works in progress On track  Works or engagement notification only  Works or engagement notification only  Works or engagement notification only  Notification Letter (PDF 240.7KB)
 Newtown Wells Street Pedestrian Safety Aug 2023 Design On track Works or engagement notification only  Works or engagement notification only  Works or engagement notification only 

Consultation (PDF 188KB)

Consultation Plan (PDF 918.6KB)

Petersham

Albert Street and

James Street Intersection

 Traffic Facilities Aug 2023 Works in progress On track Works or engagement notification only   Works or engagement notification only Works or engagement notification only  Notification Letter (PDF 122.7KB)
 Petersham

Bright Street, Middle Street,

and North Street intersection

Traffic Facilities Aug 2023 Works in progress On track  Works or engagement notification only Works or engagement notification only  Works or engagement notification only   Notification Letter (PDF 123.1KB)
Petersham

KU Petersham

Preschool

Structural rectification

building condition works

Jun 2024 Planning On track  550 - - Children's Services Work Program
Petersham Petersham Town Hall

Masterplan upgrade

 compliance works

Dec 2023 Investigation On track  70 11 42 Petersham Town Hall project
 Petersham West Street Pedestrian Safety  Aug 2023 Design On track   Works or engagement notification only Works or engagement notification only  Works or engagement notification only 

Consultation (PDF 223KB)

Consultation Plan (PDF 545.5KB)

 Summer Hill Smith Street Streetscape Improvement Works  Aug 2023 Works in progress  On track  425 - -

Consultation (PDF 122.9KB)

Consultation Plan (PDF 9.9MB)

Stanmore Northumberland Avenue Footpath Renewal  Sep 2023 Commencing On track Works or engagement notification only  Works or engagement notification only  Works or engagement notification only   Notification Letter (PDF 248.1KB)
Stanmore Sebastopol Street Footpath Renewal   Oct 2023 Works in progress  On track - - Notification Letter (PDF 107.3KB)
St Peters Canal Rd/Princess Hwy/Mary St Cycleway construction Aug 2023 Design On track 1,370  3  3 WCX M5 - Canal Rd/Princes Hwy/Mary St Cycleway
St Peters

Camdenville Park

May Street

Camdenville Park upgrade Mar 2025 Design  On track 2,515   - 5  Camdenville Park Upgrade
Sydenham Sydenham Station Cycleway construction Jun 2024 Design On track       Sydenham Station Cycleway
Tempe

Robyn Webster Building

Tempe Reserve

Refurbishment of indoor sporting facility Sep 2023 Construction On track  550 2 421 Robyn Webster Building  
 Tempe Griffith Street Footpath Renewal Aug 2023 Completed Completed  Works or engagement notification only Works or engagement notification only  Works or engagement notification only  Notification Letter (PDF 240.1KB)
 Various Urban Amenity Improvement Program
       150  (18) (17)  
 Various GreenWay Program         27,904 83 974  
 Various Roads
       9,410  244 250  
 Various Kerb & Gutter Renewal

       1,029  - -  
 Various Roadside Furniture

       200  - -  
 Various Footpaths          3,950  70 157  
 Various Traffic Facilities
         2,385  8 309  
 Various Stormwater         2,594   12 14  
 Various Bridges
         1,579  - 164   
 Various Cycleways
         778 19  
 Various Town Centres
         4,285 29 104  
 Various Sporting Ground Upgrades
         1,170  - 1  
 Various Parks Plans of Management and Masterplan         

 1,351

 10 349  
 Various Park Assets Renewal and Minor Works          865  45 74  
 Various Wharves          400  - -  
 Various Early Learning Centre
         120  - 52  
 Various Community Buildings & Libraries
         1,655  17 25  
 Various Property Buildings
         4,733  1 8  
 Various Aquatic Centres 
         1,180  - 35  
 Various Park Buildings 
         5,347  51 62  
 Various Callan Park Swim Site          200  - -  
 Various Community Wellbeing and Culture
         241  - -  
 Various Fleet
         4,615  98 288  
 Various Property & Assets
         300  18,900 18,900  
 Various ICT
         629  - 58  

Open the link below to see the projects and works completed by Council in the previous financial year:

Projects from 2022-23

Rate this page

  • Rate as The content was useful30.00% The content was useful votes
  • Rate as The content was not useful70.00% The content was not useful votes

Thanks for your feedback. We will use this data to improve the content of this page.

Page last updated: 19 Sep 2023