Dulwich Hill Station Precinct Public Domain Improvements Project

Construction updates

Project details

Project address

Wardell Rd between Ewart St and Wilga Avenue Dulwich Hill 

Objective

The Inner West Council has been funded to upgrade the Public Domain near the Dulwich Hill Station. The objective of the project is to reverse the current urban decay and deliver liveable communities and neighbourhood by providing a cohesive design surrounding the Dulwich Hill Station.

The project will deliver, a high quality multi-use corridor that will maximise connections to public transportation  and improve the amenities available for use to the public.

Project description

The proposed improvement program can be categorised into 5 main tasks:

  1. Streetscape upgrades including tree planting, multi-purpose lighting, new pavements and improved pedestrian and cyclist movements.
  2. Environmental sustainability using LED lighting, and providing shading and street trees.
  3. Creation of new plaza. Connection to the Greenway.
  4. New walking and cycling links to key transportation nodes and open spaces. These will strategically  connect local and regional transportation networks.
  5. Traffic Calming and the creation of a 40Km/hr High Pedestrian Zone.

Progress

  • Concept design complete
  • Detailed design complete
  • Tender documents are complete, and tender closed 2 May 2022
  • Underground electrical works design complete
  • Street light design is complete
  • Public Meeting and further consultation completed May/June 2022
  • Works are substantially completed     

Timing of works

The majority of works on Wardell Road are complete. Ausgrid Works are complete north of the station. All raised thresholds are completed. Architectural seating walls have been installed. Traffic signals have been installed at the intersection of Wardell and Dudley Streets and will be activated once the power is turned on. This is scheduled to occur in March/April 2024.

There have however been significant delays with adjustments and approvals for work to the Ausgrid network. Network shutdowns scheduled for June were cancelled and have led to further delays to the project. We are currently in the process of seeking approvals from Ausgrid for the remaining outages (minimum two) essential to complete the work. As part of this process, the remaining overhead wires will be removed during the scheduled outage work. Subsequently, the installation of the new multi-function poles will commence upon the completion of this phase.

All works are expected to be completed by the end of April 2024, weather permitting and subject to the completion of the remaining Ausgrid works.

Remaining works

The remaining works are largely focused on the Wardell/Ewart intersection.

Footpath paving work is scheduled to commence on Monday 4th March (weather permitted).

Undergrounding of remaining power lines at the corner of (Night-time works) will commence upon the approval of the outages.

Following this work Council’s contractor will be undertaking installation of multi-function poles, new street lighting, the commissioning of the new traffic signals and the remaining footpath works around new lights and signals.                       

Final footpath paving work is expected to finish in April 2024.

Expected completion date

April 2024

Funding

The project is funded by Inner West Council, Transport for NSW and the NSW Department of Planning and Environment.

Contact

Progress photos - Dudley Street

DH Pots re-levelled-230518

20230411_107

20230411_108

Dudley St Station works

Dudley St footpath widening

Progress photos - Wardell Road

20230411_104

20230411_105

20230411_111

Streetscape improvement works in progress

Streetscape improvement works in progress

Streetscape improvement works in progress

Streetscape improvement works in progress

Streetscape improvement works in progress

Streetscape improvement works in progress

Streetscape improvement works in progress

Streetscape improvement works in progress

Streetscape improvement works in progress

Streetscape improvement works in progress

Wardell Rd Works Aug 22

Wardell Rd Traffic Calming WIP

Pre-work photos

Wardell Road - going North near station and ped crossing

Wardell Road near Station intersection

Dulwich Hill intersection Ewart and Wardell

Concept pictures

Last updated 11/11/21.

Concept Picture Dulwich Hill Train station

Concept Picture - Dulwich Hill Train station 

Dulwich Hill concept picture Keith and Wardell Road

Concept picture: Dulwich Hill train station at the Keith/Wardell Road Intersection

Concept diagram and plan

Dulwich Hill Concept Diagram

Wardell Road Concept Diagram

Rate this page

  • Rate as The content was useful46.67% The content was useful votes
  • Rate as The content was not useful53.33% The content was not useful votes

Thanks for your feedback. We will use this data to improve the content of this page.

Page last updated: 29 Feb 2024