2025-26 park, building and road projects

Council completes a wide range of construction projects each year to deliver new and improved services to the community and maintain and renew infrastructure assets. 

In 2025-26 Council plans to deliver $128.0 million in works. As of 31 October 2025, $19.3 million has been spent. 

Search the table below for community engagement, design and works commencing or in progress.

Contact details are provided in the attached notification letter or web page link, or click on the completed projects list.

For all other related enquiries, including works at locations not listed below, contact Inner West Council on 02 9392 5000 or email council@innerwest.nsw.gov.au

Progress legend

On track – On track
Behind schedule – Behind schedule
On hold – On hold
Rescheduled – Rescheduled
Completed – Completed

Suburb Location Details Project type Budget 25/26 full year ('000) Spent Oct-25 YTD ('000) Anticipated completion Status Progress
Ashfield Ashfield Plaza Mainstreet Local Placemaking Footpath 541 -
On track
Ashfield Hammond Park Hammond Park Amenities Upgrade Community facility 566 14 March 2026 On track

Procurement of Building Services

Ashfield Hammond Park  Hammond Park Sporting Ground Upgrade Community facility  734 4 March 2026 On track Commenced
Ashfield Pratten Park Pratten Park Bowling Club   Community Facility  165 4  2028 On track  Planning 
Balmain Clontarf Cottage Roof renewal, painting and kitchen refurbishment Community facility 514 13 October 2025 On track
Commencing August 2025
Balmain Gladstone Park New Public Toilet Community facility 689 12 September 2025 On track
Construction
Balmain Illoura Reserve Aboriginal Survival Memorial Community facility 307 15 March 2026 On track
Design
Birchgrove Mort Bay Park Mort Bay Park Upgrade Community facility 1,641 104 June 2026 On track
Procurement & Design
Dulwich Hill Caves Lane

Upgrade of Caves Lane

Notification Letter (PDF 170.8KB)

Design Plan (PDF 3.1MB)

Roads and traffic 262 (25) December 2026  On track Construction 
Dulwich Hill Jack Shanahan Reserve Surface Repairs and Lighting Upgrade Community facility 631 336

Stage 1 -completed

Stage 2 -April 2026

On track

Construction

Dulwich Hill JF Laxton Reserve JF Laxton Reserve Upgrade Community facility 490 4 June 2026 On track
Design
Dulwich Hill Johnson Park Park Masterplan Upgrade Community facility  - December 2025 On track
Construction
Haberfield Richard Murden Reserve Amenities
Amenities Upgrades Community facility 400 364
Haberfield Richard Murden Reserve Inclusive Playground Community facility 382 329 June 2025 On track
Construction
Haberfield Richard Murden Reserve Netball Court Improvements  Community facility 1,031 45
Leichhardt
Blackmore Oval SES Building Building renewal works  Facility 179 - March 2026  On track  Construction
Leichhardt Leichhardt Park Aquatic Centre (LPAC) Aquatic Centre Upgrade Community facility 10,778 2,796 October 2025 On track
Design
Lilyfield Callan Park Callan Park Tidal Baths Community facility 1,977 17 On track  Design
Lilyfield Leichhardt Park Leichhardt Park Jetty Renewal Community facility 386 -
Lilyfield Lilyfield Road

Lilyfield Road Raised Pedestrian Crossings

Notification letter and detailed design (PDF 5.4MB)

Roads and traffic - - October 2025 On track
Commenced
Marrickville Annette Kellerman Aquatic Centre

Aquatic Centre Upgrade, Exterior Recladding Works, New Boiler Installation

Community facility - - Stage 1 September 2024 On track
Planning
Marrickville Henson Park

Henson Park Grandstand Redevelopment (*$12m external funding)

Community facility 8,741 551 September 2025 On track
Commenced
Marrickville Henson Park Pathway and Lighting Upgrade Community facility 200 1 Stage 1 March 2025 On track  Commenced
Marrickville Mackey Park Canoe Ramp Community facility 1,422 4 May 2025 Behind schedule
Commenced
Marrickville Mackey Park Amenities Upgrade Community facility 2,672 253 March 2026 On track
Construction commencing in September 2025
Marrickville Mackey Park Gumbramorra Swamp Re-creation Community facility 1,212 1 July 2026 On track
Construction commencing in late 2025
Marrickville Steel Park  Steel Park Sporting Ground Upgrade Community facility 2,232 15 March 2026 On track Commenced
Marrickville Wemyss Street

Kerb & Gutter, Footpath & Pavement Works 

Notification Letter (PDF 155.4KB)

Work Plans  (PDF 8.9MB)

Kerb, gutter and footpath  - - November 2025 On track
Commencing 
Newtown Lord Street

Stormwater Upgrade Works 

Notification letter  (PDF 155KB)

 
Stormwater  - - August 2025  On track
Commencing
Petersham KU Petersham

Building Refurbishment, Flood Mitigation

Community facility 520 2 December 2026 On track  Contractor Procurement
St Peters Active Transport

Road Renewal, Hogan Avenue to Gleeson Avenue

Roads and traffic - -
Sydenham Burrows Avenue and George Street

St Peters Interchange Active Transport Works: Sydenham Station Cycleway (WXC M5)

Roads and traffic - - July 2025 On track
Commenced
Tempe Kendrick Park Aboriginal Survival Memorial Community facility 280 -
Various

Playgrounds at Bill Peters Reserve, Illoura Reserve, Tom Kenny Reserve

Playground Program Community facility 118 143 June 2025 On track Construction
Various Various Playing Field Renovation Program Community 325 -
Various Various Main Street Revitalisation

Footpath, Community

5,771 61
Various Various Park Footpaths Renewal

Footpath, Community

217 -
Various Various

Pedestrian Access and Mobility Plan, Kerb Ramp Upgrades

Footpath, roads and traffic 2,205 34 June 2026 On track
Commenced
Various GreenWay

GreenWay: Active Transport and Biodiversity Corridor from Cooks to Cove

Community facility 9,125 3,603 Spring 2025 On track
Construction
 Various Leichhardt Oval 2,899 401
 Various Urban Amenity Improvement Program
1,414 -
 Various Roads 11,486 1,704
 Various Kerb & Gutter 1,480 14
 Various Footpaths
4,120 1,610
 Various Traffic Facilities
3,784 172
 Various Stormwater
4,947 621
 Various Car Parks
61 4
 Various Bridges
320 (1)
 Various Cycleways
4,480 158
 Various Town Centres
3,001 179
 Various Main Street Local Placemaking
168 2
 Various Sporting Ground Upgrade 514 65
 Various Playground Strategy Program
3,420 397
 Various Parks Plans of Management and Masterplan Program
1,844 274
 Various Park Assets Renewal and Minor Works
2,065 159
 Various Floodlighting Program
1,250 8
 Various Early Learning Centre
968 46
 Various Community Buildings & Libraries
3,701 134
 Various Property Buildings 7,180 417
 Various Aquatic Centres 
124 13
 Various Park Buildings   4,947 237
 Various Sea Walls
114 -
 Various Community Wellbeing and Culture
- -
 Various Fleet
4,849 3,286
 Various ICT
588 -

Completed projects

Suburb Location Details Project type Budget ('000) Spent YTD ('000) Completion Status Progress
Ashfield Ashfield Civic Centre Building Upgrades Community facility 834 509 October 2025  Completed Completed
Balmain Dawn Fraser Baths  Northern Pavilion Refurbishment Community facility 779 170 October 2026 Completed  Completed
Lilyfield Leichhardt Park Pathway Construction of new 150m pathway through Leichhardt Park between Mary Street and Frazer Street Community facility - - July 2025 Completed
Completed
 Annandale Annandale Town Hall  Building Refurbishment  Community facility  -  -  July 2025  Completed Completed
 Lilyfield The Boulevarde

Road and Pedestrian Safety Improvement Works

Notification Letter (PDF 105.5KB)

Design Plans (PDF 13.3MB)

Roads and Traffic   - -

November 2025

 Completed Completed

Previous years

Open the links below to see the projects and works completed by Council in previous financial years:

Projects from 2024-25

Projects from 2023-24

Projects from 2022-23

Service unit performance reporting

You can also view the service unit performance reporting page here:

Service unit performance reporting