2024-25 park, building and road projects

Council completes a wide range of construction projects each year to deliver new and improved services to the community and maintain and renew infrastructure assets.

In 2024-25 Council plans to deliver $99.9 million in works. As at 31 May 2025, $74.7 million has been spent.

Search the table below for community engagement, design and works commencing or in progress.

Contact details are provided in the attached notification letter or web page link, or click on the completed projects list.

For all other related enquiries, including works at locations not listed below, contact Inner West Council on 02 9392 5000 or email council@innerwest.nsw.gov.au.

Progress legend

On track – On track
Behind schedule – Behind schedule
On hold – On hold
Rescheduled – Rescheduled
Completed – Completed

Suburb Location Details Project type Budget 24/25 full year ('000) Spent YTD ('000) Anticipated completion Status Progress
Annandale Annandale Town Hall Building Refurbishment Community Facility 878 276 July 2025 On track
Construction
Annandale Young Street

Rock Wall Renewal, Hutchinson Street to Hudson Street

Community -  -      
Ashbury Hanks Street

Traffic Facilities and Road Renewal, Holden Street to Old Canterbury Road

Road, Traffic

374 144    
Ashfield Albert Street

Road Renewal, Frederick Street to Alt Street

Road 275 274      
Ashfield Ashfield Civic Centre Building Upgrades Community Facility 314 269 September 2025 On track
Design
Ashfield Ashfield Plaza Mainstreet Local Placemaking Footpath 123 1

 
Ashfield Hammond Park Hammond Park Amenities Upgrade Community Facility 90 63 March 2026 On track

Procurement of Building Services

Ashfield Hammond Park Hammond Park Sporting Ground Upgrade Community Facility  640 - March 2026 On track Construction commencing September 2025
Ashfield Hardy Street

Road Renewal, Queen Street to Griffiths Street

Road 270 13  
 
Balmain Curtis Road Roundabout Town Centre Upgrade

Road

Traffic

50 -  
 
Balmain Dawn Fraser Baths Northern Pavilion Refurbishment Community Facility 202 78 June 2027 On track
Design
Balmain Gladstone Park New Public Toilet Community Facility 593 63 August 2025 On track
Construction
Balmain Illoura Reserve Aboriginal Survival Memorial Community Facility 215 72 August 2025 On track
Design
Balmain Wortley Street

Stormwater Drainage Improvements

Notification Letter (PDF 1.4MB)

Stormwater 160 160   On track
Commencing
Birchgrove Mort Bay Park Mort Bay Park Upgrade Community Facility 539 35 June 2026 On track
Procurement and design
Dulwich Hill Jack Shanahan Reserve Surface Repairs and Lighting Upgrade Community Facility 642 20

Stage 1 August 2025

Stage 2 October 2025

On track

Construction

Dulwich Hill JF Laxton Reserve JF Laxton Reserve Upgrade Community Facility 10 6 June 2026 On track
Design
Dulwich Hill Johnson Park Park Masterplan Upgrade Community Facility  - Spring 2025 On track
Construction
Dulwich Hill Pigott Street

Road Renewal

New Canterbury Road to Denison Street

Road 100 5   On track
 
Haberfield Richard Murden Reserve Amenities
Amenities Upgrades Community Facility 400 -


Haberfield Kingston Street

Drainage Upgrade

Deakin Street Intersection

Notification Letter and Plan (PDF 9.6MB)

Stormwater 520 5 October 2025 On track
Commencing
Haberfield Richard Murden Reserve Inclusive Playground Community Facility 1,999 465 June 2025 On track
Construction
Haberfield Richard Murden Reserve Netball Court Improvements Community Facility - -
On track
Design
Leichhardt Catherine Street Depot Refurbishments Community Facility 285 240      
Leichhardt Lambert Park Playground Renewal Community Facility 220 247      
Leichhardt Leichhardt Park Aquatic Centre (LPAC) Aquatic Centre Upgrade Community Facility 3,500 1,231 October 2025 On track
Design
Lilyfield Callan Park Callan Park Tidal Baths Community Facility 200 110
On track Design
Lilyfield Leichhardt Park Leichhardt Park Jetty Renewal Community Facility 10 -
On track
 
Lilyfield Lilyfield Road

Lilyfield Road Raised Pedestrian Crossings

Notification Letter and Detailed Design (PDF 5.4MB)

 

Road

Traffic

    October 2025 On track
Commenced
Lilyfield The Boulevarde

Road Reconstruction and Tree Planting, Balmain Road to Joseph Street

Road

Kerb and Gutter

- 7

 
Marrickville Annette Kellerman Aquatic Centre

Aquatic Centre Upgrade

Exterior Recladding Works, New Boiler Installation

Community Facility 810 907 Stage 1 September 2024 On track
Planning
Marrickville Henson Park

Henson Park Grandstand Redevelopment

*$12m external funding

Community Facility 1,900 659 September 2025 On track
Commenced
Marrickville Henson Park Pathway and Lighting Upgrade Community Facility 280 319 Stage 2 March 2025 On track  Commenced
Marrickville Mackey Park Canoe Ramp Community Facility 821 464 November 2025 Behind schedule
Commenced
Marrickville Mackey Park Amenities Upgrade Community Facility 240 227 March 2026 On track
Construction commencing in September 2025
Marrickville Murray Street

Road Renewal

Victoria Road to Edinburgh Road

Road - 17      
Marrickville Northcote Street Stormwater Drainage Upgrade Stormwater 235 179      
Marrickville Smidmore Street

Road Renewal

Murray Street to Edgeware Road

Road 150 13      
Newtown Lord Street

Stormwater Upgrade Works 

Notification Letter  (PDF 155KB)

 
Stormwater  - - August 2025  On track
 Commencing
Newtown Peace Park Main Street Local Placemaking Community Facility 445 463      
Petersham KU Petersham

Building Refurbishment

Flood Mitigation

Community Facility 24 34
On track  Design
Rozelle
Denison Street

Road Renewal

Darling Street to Burt Street

Road - -      
Rozelle Hancock Lane Main Street Local Placemaking

Footpath

Community Facility

195 226      
St Peters Active Transport

Road Renewal

Hogan Avenue to Gleeson Avenue

Road 290 15      
St Peters Grove Street Unwins Bridge Road to Princes Highway Road 110 27      
Sydenham Burrows Avenue and George Street

St Peters Interchange Active Transport Works

Sydenham Station Cycleway (WXC M5)

Cycleway
Sydenham Station to Mary Street

 Traffic 1,361 700 July 2025 On track
Commenced
Tempe Bay Street

New Footpath

Princes Highway to Old Street

Road

Footpath

150 156      
Tempe Kendrick Park Aboriginal Survival Memorial Community Facility - -      
Tempe Various

Road Renewal

Laneways along Henry Street

Road 250 4   On track
 
Various

Bill Peters Reserve Playground

Illoura Reserve Playground

Tom Kenny Reserve Playground

Playground Program Community Facility 1,206 998 June 2025 On track Construction
Various Various Playing Field Renovation Program Community 242 120      
Various Various Main Street Revitalisation

Footpath

Community

1,008 998   On track
Planning
Various Various Small Span Bridge Rehabilitation  Road - -      
Various Various Park Footpaths Renewal

Footpath

Community

15 15      
Various Various

Pedestrian Access and Mobility Plan

Kerb Ramp Upgrades

Footpath

Traffic

1,735 1,671 June 2026 On track
Commenced
Various GreenWay

GreenWay

Active Transport and Biodiversity Corridor from Cooks to Cove

  29,490 22,949 Spring 2025 On track
Construction
Various Various Great Inner West Walk

Footpath

Community

50 -      
Various Urban Amenity Improvement Program     100 55      
 Various Leichhardt Oval
    510 471      
 Various Roads     6,197 5,495      
 Various Kerb & Gutter Renewal     571 471      
 Various Footpaths     4,030 2,498      
 Various Traffic Facilities     1,375 1,185      
 Various Stormwater     2,187 1,486      
 Various Car Parks     97 91      
 Various Bridges     335 64      
 Various Cycleways     890 502      
 Various Town Centres     455 448      
 Various Sporting Ground Upgrade     140 121      
 Various Parks Plans of Management and Masterplan Program      240 49      
 Various Park Assets Renewal and Minor Works
    501 322      
 Various Floodlighting Program
    40 19      
 Various Early Learning Centre
    235 147      
 Various Community Buildings & Libraries
    1,087 527      
 Various Property Buildings     2,185 812      
 Various Aquatic Centres 
    170 176      
 Various Park Buildings 
    495 (2)      
 Various Community Wellbeing and Culture     30 23      
 Various Fleet
    4,397 4,433      
 Various ICT     50 64      

Completed projects

Suburb Location Details Project type Budget ('000) Spent YTD ('000) (Jan 24) Completion Status Progress
Ashfield

Ashfield Park

Sporting Ground Sand Grooving Community Facility - - October 2024 Completed
Completed
Ashfield Elizabeth Street

Road Reconstruction and Footpath Improvements

Liverpool Road to Bland Street

 Road

Kerb and Gutter

Footpath

Traffic

507 602 July 2024 Completed
Completed
Balmain  Balmain Town Hall Town Hall and Library upgrade Community Facility 1,247 1,339 August 2024 Completed
Completed
Balmain Darling Street

Main Street Improvements at Elliott Street Intersection

Footpath

Traffic

510 410 March 2025 Completed
Completed
Balmain Paringa Reserve Elliot Street Kiosk Community Facility 1,047 990 FY 2024/25 Completed
Completed
Balmain East Datchett Street Reserve

Demolition of Incinerator at Datchett Street Reserve

Community Facility 23 16 December 2024 Completed
Completed
Croydon Centenary Park Sporting Ground Sand Grooving
Community Facility
- - October 2024
Completed
Completed
Dulwich Hill Hoskins Park Park Upgrade
Community Facility 718 809 January 2025 Completed Completed
Haberfield  Algie Park Sporting Ground Sand Grooving
Community Facility
 - - October 2024 Completed Completed
Leichhardt Blackmore Oval Floodlighting Upgrade Community Facility
145
157 March 2025 Completed
Completed
Lilyfield Leichhardt Oval No2 Leichhardt Oval No2 Amenities Upgrade Community Facility 1,083 1,007 October 2024 Completed
 Completed
Lilyfield

Leichhardt Oval No2

Waterfront Drive

Embankment extension and Sporting Ground Sand Grooving Community Facility - - October 2024 Completed
Completed
Marrickville Centennial Street

Stormwater Upgrade

Stormwater 51 65 October 2024 Completed
Completed
Marrickville Mackey Park Sporting Ground Upgrade Community Facility 1,850 1,882
March 2025 Completed
Completed
Newtown King Street

Traffic Facilities

Traffic

July 2024 Completed
Completed
Newtown Laura Street

Pedestrian Crossing Upgrade

Traffic - - October 2024 Completed
Completed
Newtown Newtown Town Hall Town Hall Renewal Community Facility 350 461 August 2024 Completed
Completed
Newtown Peace Reserve Peace Reserve Upgrade Community Facility     December 2024 Completed Completed 
Rozelle King George Park Amenities Upgrade Community Facility 1,565 1,109 November 2024 Completed
Completed
Rozelle
King George Park Inclusive Playground Community Facility 1,893 1,968 September 2024 Completed
Completed
St Peters Camdenville Park Camdenville Park Amenities Refurbishment Community Facility
1,485
958
May 2025 Completed
Completed
St Peters Camdenville Park Camdenville Park Upgrade Community Facility 5,476 5,459 April 2025 Completed
Completed
St Peters Various

St Peters/Tempe

Footpath Improvements

Footpath 800 1,045 FY 2024/25 Completed
Completed
Tempe Griffiths Street Road Resurfacing Road

July 2024 Completed
Completed
Tempe Tempe Reserve

Tempe Reserve Amenities Building Refurbishment

Alexandria Canal Modular Sporting Amenities Refurbishment

Community Facility 1,750 2,045 FY 2024/25 Completed
Completed

Previous years

Open the links below to see the projects and works completed by Council in previous financial years:

Projects from 2023-24

Projects from 2022-23

Service unit performance reporting

You can also view the service unit performance reporting here:

Service unit performance reporting

Rate this page

  • Rate as The content was useful0% The content was useful votes
  • Rate as The content was not useful0% The content was not useful votes

Page last updated: 06 Aug 2025