Traffic Facilities Program

Project Description

Council  delivers a program of traffic and pedestrian infrastructure upgrades in the local area to improve road safety and traffic movement. This includes:

  • Improving and building new pedestrian crossings & refuges;
  • Speed cushions and speed humps;
  • Kerb extensions  and  blisters;
  • Median islands

Major projects require designs to be completed and approval by the Local Traffic Committee (LTC) and Council. See current Council Meeting  dates for details for LTC and Council meetings and business papers.

Information can also be found on the Inner West Council Your Say page 

Expected Completion

June 2023

Budget

 $2.56m These projects are funded by Inner West Council, Transport for NSW and the NSW Government Local Roads and Community Infrastructure Program

Project address

Various across council 

Contacts

A. Hyde Page, (02) 9392 5262,  alistair.hyde.page@innerwest.nsw.gov.au

C. Phillips,  (02)9392 5644, chrisine.phillips@innerwest.nsw.gov.au

I. Alaloul, (02) 9392 5263, Imad.alaloul@innerwest.nsw.gov.au

M. Bye, (02) 9392 5158,  mark.bye@innerwest.nsw.gov.au

P. Gudelj, (02) 9392 5801, predrag.gudelj@innerwest.nsw.gov.au

P. Lunnis, (02) 8595 2423, paul.lunniss@innerwest.nsw.gov.au

S Bakovic, (02) 9335 2228, snezana.bakovic@innerwest.nsw.gov.au

For all other enquiries contact Inner West Council on 9392 5000 or email council@innerwest.nsw.gov.au

Notifications

Community notifications will be provided to all residents before works commence in each location. The notifications will also be available on this page.

 

Progress legend

On track Green: On track
Behind schedule Amber: Behind schedule
On hold Red: On hold
Rescheduled Blue: Rescheduled
Completed Purple: Completed

 
Suburb Location Type of work Program  Anticipated completion Status Progress Further information
 Annandale

Annandale Street

Piper Street

 Pedestrian Crossing  Pedestrian Safety June 2022 Completed Completed  Annandale Street notification (PDF 260.1KB)
 Ashfield

Alt Street

Elizabeth Street

Kerb and Gutter improvements  Speed Cushions May 2022 Completed Completed  Alt Street notification (PDF 322.2KB)
Ashfield

Church Street

Lucy Street

 Kerb and Gutter improvements Intersection Improvements May 2022 Completed  Completed

 Church St Notification (PDF 322.4KB)

Ashfield Harland Street Kerb and Gutter improvements Construction of new Speed cushion and Kerb Blister Feb 2022 Completed Completed Harland Street notification(PDF 813.9KB)
Ashfield Arthur Street Kerb and Gutter improvements Construction of new Speed cushion and Kerb Blister  Jun 2022 Completed Completed Arthur St  notification (PDF 164.2KB)
Balmain  Cameron Street  Kerb and Gutter improvements

Street Parking Improvements 

adjusting kerb and indented parking bays

 Jul 2022  Engagement  On track 

 Consultation (PDF 222.9KB)

Consultation Plan (PDF 1.1MB)

Balmain Stephen Street Kerb and Gutter improvements   Parking Improvements May 2022 Engagement On track 

Consultation (PDF 886.4KB)

Consult Plan (PDF 1.3MB)

 Balmain Wallace Street Kerb and Gutter Improvements Parking Improvements May 2022 Engagement On track 

 Consultation (PDF 864.8KB)

Consult Plan (PDF 1.2MB)

Croydon

Thomas Street

Edwin Street

Kerb and Gutter improvements
Intersection Improvements  May 2022 Completed Completed

Thomas Street notification (PDF 250.4KB)

 Haberfield Tillock Street Footpath Improvements Footpath Renewal 2022/2023 FY Planning On track  Notification letter - Tillock Street Haberfield (PDF 699.5KB)

Notification Plan- Tillock Street Haberfield (PDF 484.4KB)

Leichhardt

Kegworth &Tebbutt Street

Pedestrian Crossing Pedestrian Safety Dec 2021 Engagement Completed

Consultation(PDF 892KB)

Consult Plan (PDF 1.2MB)

Leichhardt

Lord &

Flood Street roundabout

Pedestrian Crossing  Upgrading of two existing pedestrian crossings Jun 2022 Completed Completed Lord Street notification (PDF 258.9KB)
Lewisham Toothill and Victoria Street Raised Pedestrian Crossing Pedestrian Safety Jan 2022 Completed Completed Toothill Street  notification (PDF 164.4KB)
Leichhardt

Marion Street 

145A-159 North side 

 Footpath improvements Footpath Renewal   Dec 2021 Engagement Completed   Consultation letter - Marion Street (PDF 222.4KB)

Consultation plan - Marion Street (PDF 339.5KB)

Marrickville Addison Road Footpath Improvements Pedestrian Safety Dec 2021 Engagement  Completed

Consultation Letter (PDF 854.7KB)

Consultation plan  (PDF 837.1KB)

Marrickville Illawarra Road Footpath Improvements

Footpath Renewal

2022/2023 FY

Planning

On track  
Marrickville Neville Street  Footpath Improvements Footpath Renewal 2022/2023 FY  Planning  On track  Consultation Letter - Neville Street (PDF 245.6KB)
 Marrickville Warren Road One Way Treatment Pedestrian Safety
 Apr 2022  Completed Completed

 Warren Road Project page 

Your Say page

Newtown Holmwood Street Footpath Improvements
Footpath Renewal May 2022 Completed Completed Holmwood Street notification (PDF 194.8KB)
 St Peters Church Street   Kerb and Gutter improvements Kerb & Gutter 2022/2023 FY Planning On track  Adjacent to St Peters Public School
St Peters

Unwins Bridge Road

Signalised Crossing Pedestrian Safety Jun 2022  Planning On track  Unwins Bridge Road Crossing Project page
Stanmore

Holt Street

Cambridge Street

Raised Pedestrian Crossing Pedestrian Safety Jul  2022  Works Commencing On track   Holt Street notification (PDF 251.7KB)
 Tempe Bay Street Footpath Improvements Footpath Renewal  2022/2023 FY  Planning  On track  

Rate this page

  • Rate as The content was useful0% The content was useful votes
  • Rate as The content was not useful0% The content was not useful votes

Thanks for your feedback. We will use this data to improve the content of this page.

Page last updated: 09 Nov 2022