Annette Kellerman Aquatic Centre Upgrade

Capital Works Project: Annette Kellerman Aquatic Centre Upgrade
  • Project address: Annette Kellerman Aquatic Centre, Black Street, Marrickville
  • Project description: This project is to replace end of life plant at the aquatic centre and improve sustainability and energy performance. Planned works include:
  • Stage 1: 
    Replacement of aluminium composite cladding on roof structure.
  • Stage 2:
    Replacement of heating and cooling plant with fully electrified heat pump and chiller system.
    Expand existing solar panels.
    Roof louvre and skylight replacement.
  • Progress: Stage 1 works are completed, and stage 2 works are in the planning phase.
  • Expected timeframes: Stage 1: January 2024-October 2024, Stage 2: April 2028- September 2028
  • Budget: Stage 1: $2M
  • Contact: Alex Nord on 02 9335 2191 or alex.nord@innerwest.nsw.gov.au
Page last updated: 17 Apr 2026