Footpaths, roads, traffic and stormwater monthly report

You can find the monthly reporting relating to  footpaths, roads, traffic and stormwater below.

Current report: September 2018

Project status:

Green  Green: Planning, design and/or construction progressing as per schedule
Green  Amber: Planning, design and/or construction delayed with respect to the original schedule
Green  Red: Planning, design and/or construction on hold or cancelled

Capital Program Footpaths, Roads, Traffic and Stormwater 2018/19 Budget ($'000) Actual ($'000) % spent Forecasted year end expenditure ($'000) Project status Commentary 2019/20 ($'000) 2020/21 ($'000) 2021/22 ($'000)
Road Renewal Arthur St - Road Reconstruction
(Holden St to Milton St)
850 - - 850 Green
Documentation being finalised for request of tenders for construction works - - -
Denman Ave Traffic Works 80 - - 80 Green
Construction works commenced in October 2018 - - -
Blackmore Oval Wetland Stormwater Upgrade - 135 - - Green
Construction of wetland and stormwater recycling for irrigation completed September - - -
Marrickville Valley FRMSP Works - - - - - - 100
Booth Street Bridge - Investigation Design and Replacement 840 7 1% 840 Green
Design in progress. - - -
Lilyfield Road Cycleway 1,500 - - 1,500 Amber
Finalising tender documentation for design review /development. 2,375 - -
Bike Route RR (Longport St to Eliza St) Construction - - - - Green
Design of intersection traffic signal modifications in progress. 2,000 2,500 2,200
Ashfield Town Centre Upgrade 295 454 154% 295 Green
Stage 1 Construction in progress with anticipated practical completion in October 1,000 - -
Marrickville Rd Centre Design and Implementation 195 - - 195 Green
Design project - preferred consultant selected for appointment in September - 500 1,100
Annandale Main street outside Post Office - 4 - - - - -
Regional Roads Renewal - Capital 845 11 1% 845 Green
Tendering for the construction works in progress 850 860 1,000
Local Roads Renewal - Capital 4,834 64 1% 4,834 Green
Road resurfacing at Petersham Rd (Centennial St to Marrickville Rd), Marrickville, following drainage upgrades is in progress.
Works for Stage 1 of resurfacing program scheduled to December 2018.
5,294 5,289 5,248
Kerb & Gutter Renewal - Capital 544 73 13% 544 Green
Design in progress. 400 405 370
Roadside Furniture - Capital 100 4 4% 100 Green
Tenders invited for the reconstruction of barrier fencing at Junction St, Marrickville 100 188 100
Footpaths Renewal - Capital 2,342 264 11% 2,342 Green
Renewal completed at O'Neill Street, Lilyfield; Constitution Rd, Keith St and from end of Bedford Cres to Keith Ln, Dulwich Hill; Barker St, Lewisham; Frederick St and Trafalgar Street , Petersham; Marshall St, Stanmore; Barclay St and Albermarle St West, Marrickville.
Renewal works in progress at Macaulay Rd (Bridge Rd to Northumberland Ave), Stanmore and Elswick St (Railway St to Crystal St), Petersham.
2,200 2,130 2,511
Footpaths Upgrade - Capital 65 - - 65 Green
Scoping in progress for Bus stop modifications to improve accessibility 250 260 144
Traffic and Parking Management - Capital 160 6 3% 160 Green
Local Area Traffic Management Scheme reviews currently in progress for Newington and Newtown precincts. 165 165 165
Traffic Facilities- Capital 1,976 65 3% 1,976 Green
Completed the construction of raised pedestrian crossing at Chapel St near Illawarra Rd, Marrickville, pedestrian crossing and traffic calming improvements at Denman Ave between Dalhousie St and Alt St, Haberfield, speed hump at Perimeter St (Mary St) near Glover St, Lilyfield; Pedestrian Refuge Islands at Williams Pde near Constitution Rd, Dulwich Hill 1,178 366 992
Stormwater Renewal - Capital 1,090 33 3% 1,090 Green
Tenders called for renewal works at 7 locations.
Project scoping for the remaining locations in progress.
1,345 959 1,450
Stormwater Upgrade - Capital 1,195 33 3% 1,195 Green
Project scoping, design and tendering of various stormwater upgrade projects in progress including: Water Sensitive Urban Design facilities at Darley Rd, Leichhardt; upgrade works at O'Conner Reserve, Rozelle, and Longview St, Balmain; upgrade works and replacement of stairs at Johnson St, Balmain East.
Drainage improvements at Riverside Crescent, Marrickville; banks stabilisations at Dibble Avenue Waterhole, Marrickville.
786 565 1,345
Bridges - Capital 300 - - 300 Green
Works for the replacement of the footbridge at Chester St in progress 35 - 375
Cycleways - Capital 1,725 2 0% 1,725 Amber
Design of Bike Route LR18 (Mvle Station to Dulwich Hill) completed. Cycleway program under review due to unsuccessful grant outcomes 1,375 1,045 3,526
Car Parks - Capital 260 - - 260 Green
Public engagement on the proposed design for the refurbishment of Lennox Street Carpark in progress. 35 180 285
Town Centres Upgrade- Capital 1,784 - - 1,784 Green
Design of Gateway treatments (Ashfield Town Centre) in progress. Design and consultation in progress for streetscape upgrade Darling St (Red Lion to Denison St) 140 590 1,920
Urban Amenity Improvement Program 930 - - 930 Green
Masterplan due for public exhibition in December. 6,718 16,678 -
Total Footpaths, Roads, Traffic and Stormwater 21,910 1,156 5% 21,910 26,246 32,679 22,831

Rate this page

  • Rate as The content was useful16.67% The content was useful votes
  • Rate as The content was not useful83.33% The content was not useful votes

Thanks for your feedback. We will use this data to improve the content of this page.

Page last updated: 30 Oct 2018