Community services and culture monthly report

Current report: March 2020

Project status:

Green  Green: Planning, design and/or construction progressing as per schedule
Green  Amber: Planning, design and/or construction delayed with respect to the original schedule
Green  Red: Planning, design and/or construction on hold or cancelled

Capital Program 2019/20 Budget ($000) 2018/19 Unfinished Projects Actual ($000) % Spent Forecasted Year End Expenditure ($'000) Project Status Commentary Delivery Date 2020/21 ($'000) 2021/22 ($'000) 2022/23 ($'000)
Arts Projects 231 118 72 20% 355 Green Various projects. 50% completed and remaining 50% underway Various
Mervyn Fletcher Community Centre renewal works 600 174 442 104% 424 Green Completed Completed - - -
Capital Program Community Services 1,371 472 843 65% 1,295 Green Petersham Town Hall entry tender assessment in progress and caretakers egress complete. Steel Park Community Room and renewal works at Mervyn Fletcher Community Centre and Thirning Villa Pratten Park completed. RFQ preparation for Newtown Town Hall masterplan in progress. Various 3,070 924 3,626
Total Community Services & Culture 2,202 764 1,356 65% 2,074 3,070 924 3,626


Rate this page

  • Rate as The content was useful0% The content was useful votes
  • Rate as The content was not useful0% The content was not useful votes

Thanks for your feedback. We will use this data to improve the content of this page.

Page last updated: 01 May 2020