Project information
- Project description: The proposed upgrade works include: Improve fields surface and new turf; upgrade irrigation; drainage improvements; upgrade floodlighting; cricket wicket upgrade and fencing upgrade.
- Project address: 531-565 Illawarra Rd, Marrickville NSW 2204
- Progress: Construction in progress
- Expected completion date: March 2026 (weather permitting)
- Budget: $1,760,000.00
- Contact: Gabriela Ortega on (02) 9392 5429 or gabriela.ortega@innerwest.nsw.gov.au
Progress:
Steel Park construction is now gathering momentum.
- Existing Cricket Pitch preparation for a new synthetic turf cover.
- Base grading completed and turf preparation of the field in progress.
- Irrigation upgrades in progress.
- Existing light towers removed and new electrical services being installed, readying for light tower installation.




Page last updated: 05 Mar 2026