Steel Park Sporting Ground Upgrade

Capital Works Project: Steel Park Sporting Ground Upgrade

Project information

  • Project description: The proposed upgrade works include: Improve fields surface and new turf; upgrade irrigation; drainage improvements; upgrade floodlighting; cricket wicket upgrade and fencing upgrade.
  • Project address: 531-565 Illawarra Rd, Marrickville NSW 2204
  • Progress: Construction in progress
  • Expected completion date: March 2026 (weather permitting)
  • Budget: $1,760,000.00
  • Contact: Gabriela Ortega on (02) 9392 5429 or gabriela.ortega@innerwest.nsw.gov.au

Progress:

Steel Park construction is now gathering momentum.

  • Existing Cricket Pitch preparation for a new synthetic turf cover.
  • Base grading completed and turf preparation of the field in progress.
  • Irrigation upgrades in progress.
  • Existing light towers removed and new electrical services being installed, readying for light tower installation.

Steel Park Sporting Upgrade

Field final earthworks “Trimming” in preparation of turf

Soccer field with players on the pitch.

Root mapping

Page last updated: 05 Mar 2026